Overview
Sector: Public Sector
Project: Ingeus, DWP
Duration: 38 week programme
Scope of works:
- Electrical & Mechanical upgrades
- Proposal development
- Site assessment and analysis
- Testing and commissioning
- Documentation and handover
Challenges
Tight project timelines: Challenges include meeting strict project timelines influenced by client requirements, construction schedules, and budget constraints.
Coordination with other trades: This coordination can be challenging due to differences in schedules, conflicting priorities, and the need for effective communication and collaboration.
Adherence to safety regulations: Work involves inherent risks, and we must ensure compliance with safety regulations and codes.